Q.
What are the highlights of UMPP?
Ultra
Mega Power Projects (UMPP) were launched to meet the growing needs of
the economy, achieve power at low tariff, cater the needs of more
than one states and to make swift capacity addition.
These
are very large sized projects, approximately 4000 MW each involving
an estimated investment of about $ 4 billion. The projects envisage
to substantially reduce power shortages in the country.
These
projects are being developed on a Build, Own, and Operate (BOO)
basis. Power Finance Corporation (PFC) has been designated as nodal
agency. PFC has to create a project specific Special Purpose Vehicle
(SPV), which in turn will perform the bidding process for the
project.
Following
are the salient features of this initiative:
The
Ultra Mega Power Projects would use Super Critical Technology with a
view to achieve higher levels of fuel efficiency, which results in
fuel saving and lower green-house gas emissions.
Flexibility
in unit size subject to adoption of specified minimum Supercritical
parameters.
Integrated
power project with dedicated captive coal blocks for pithead
projects.
Coastal
projects to use imported coal.
Q.
What is the Concept of Shell Companies (SPVs) and its
Operationalisation?
The
preliminary project development activities including tie up of
various inputs / clearances are to be carried out by the respective
SPVs. These SPVs, alongwith the various clearances, tie ups, etc. are
subsequently transferred to the selected project developer.
Some
of the main activities undertaken by the SPVs are:
Appointment
of Consultants to undertake preparation of Project Report,
preparation of Rapid Environment Impact Assessment Report and to
conduct other studies as required etc.
To
finalise RfQ/ RfP documents in consultation with States / bidders
To
carry out RfQ/ RfP process and award of project Acquisition of land
for the project as per requirement of bidding guidelines Obtaining
allocation of Coal blocks for pit-head projects
Getting
clearance regarding allocation of water by the State Govt. for
pit-head locations
Approval
for use of sea water from Maritime Board/ other Govt. Agencies for
coastal locations
Obtain/initiate
environment and forest, clearances etc. as per requirement of Bidding
Guidelines.
Obtaining
geological reports/ other related data from CMPDI for the coal blocks
Signing
of Power Purchase Agreements with Procurers.
Q.
What is the Status of UMPP?
Four
UMPPs namely Sasan in Madhya Pradesh, Mundra in Gujarat,
Krishnapatnam in Andhra Pradesh and Tilaiya in Jharkhand have been
awarded to the identified developers.
Furthermore,
Request for Qualification (RfQ) for two more UMPPs one in Sarguja
District of Chhattisgarh and another at Bedabahal in Sundergarh
District of Orissa have already been issued. Sites in respect of
Tamil Nadu UMPP and Andhra Pradesh Second UMPP have been identified.
Efforts are being made to bring them to bidding stage at the
earliest. Sites selection processes are on for setting up of more
UMPPs in different states like Jharkhand, Orissa, Tamil Nadu and
Gujarat etc.